从本期开始,我们将开始对FIDIC1999施工合同文本Conditions of Contract for Construction中的"14 Contract Price and Payment(合同价格和付款)"条款进行翻译、点评.鉴于合同价格和付款在工程合同中的重要性,这个条款内容非常丰富.FIDIC1999施工合同文本中这个条款下包括了15个子款,分别是:
14.1 The Contract Price合同价格;
14.2 Advance Payment预付款;
14.3 Application for Interim Payment Certificates中期付款证书的申请;
14.4 Schedule of Payments付款计划表;
14.5 Plant and Materials Intended for the Works用于工程的设备和材料;
14.6 Issue of Interim Payment Certificates中期付款证书的颁发;
14.7 Payment付款;
14.8 Delayed Payment延误的付款;
14.9 Payment of Retention Money保留金的支付;
14.10 Statement of Completion竣工报表;
14.11 Application for Final Payment Certificate最终付款证书的申请;
14.12 Discharge结清证明;
14.13 Issue of Final Payment Certificate最终付款证书的颁发;
14.14 Cessation of Employer's Liability业主责任的中止;
14.15 Currencies of Payment支付的货币.